This is directly from the handout. (sorry I don't have a scanner handy)
August 2014-Spring 2016
Orangethorpe Ave Road Closure
OCTA previously planned for the bridge to be built while Orangethorpe remained open via a bypass road with one lane in both directions. However, complex utility relocations have affected the construction schedule. In order for the project to remain on schedule for completion by spring 2016, Orangethorpe Ave will be fully closed while the bridge is under construction. Starting early 2015, access to Chapman Ave will be closed until approximately late 2015.
Drivers can use either Kraemer Blvd to the west or Tustin/Rose to the east, with Alta Vista St to the north and Miraloma to the south, as detour routes.
For more information:
Tresa Oliveri
OC Bridges Outreach Manager
toliveri@octa.net
714-560-5374
OCTA
550 S. Main St.
P.O. Box 14184
Orange CA 92863
The Board met with Tresa and voiced many of our concerns. She was supposed to get back to us with some answers soon. If you have concerns, please let us know and/or let Tresa know.
And here are the notes that Lynne Waterson (our board secretary) took from our meeting with Tresa.
Schedule is behind. Delays in relocating utility lines
Bypass road not being utilized now, alternative close Orangethorpe Avenue
Until 2016, starting early August.
Chapman Avenue open until January 2015 then closed for 9 months to a year.
August 11th sound blanket structure on Orangethorpe starting
OCTA own the whole project until completion then turned over to the City of Placentia.
Will give updates as and when available. Can go on website and check updates.